Friday, November 15

York Road Streetscape Update: November 18-November 29



WORK PLANNED FOR NOVEMBER 2013 (weather permitting)



Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
                      9:00 am to 3:00 pm (intersection at Cold Spring)
           
Tentative Schedule:

11/18-11/20/13: Mill Cold Spring, Old Cold Spring (patch) & crosswalks at 43rd St

11/20-11/22:  Pave milled areas

11/25-11/29 (no work 11/28): minor concrete repairs and landscaping maintenance throughout project limits


Thank you in advance for your cooperation. For additional information or questions regarding this
work, please contact Mrs. Jessica Lewis at 410 396-6956/6957.  

 The Department of Transportation: “Keeping Baltimore Moving Safely”