York Road Streetscape Update: November 18-November 29
WORK PLANNED FOR NOVEMBER 2013
(weather permitting)
Contract TR-10319- York Road
Rehabilitation
Limits: York Rd from 43rd Street to Glenwood Avenue
Work Hours: 8:00 am to 3:00 pm
(northbound only - As per Robert Ferguson)
9:00 am to 4:00 pm (southbound only -
As per Robert Ferguson)
9:00 am to 3:00 pm (intersection at
Cold Spring)
Tentative Schedule:
11/18-11/20/13: Mill Cold Spring, Old Cold Spring (patch)
& crosswalks at 43rd St
11/20-11/22: Pave
milled areas
11/25-11/29 (no work 11/28):
minor concrete repairs and landscaping maintenance throughout project limits
Thank you in
advance for your cooperation. For additional information or questions regarding
this
work, please
contact Mrs. Jessica Lewis at 410 396-6956/6957.