Monday, April 30

York Road Streetscape Update: Week of April 30




WORK PLANNED FOR UPCOMING WEEK (weather permitting)

April 30 – May 4, 2012


Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
           

  • Monday-Friday: Temporary (moveable) Northbound lane closures for concrete work (sidewalk, curb, driveways) on York Road from E. Cold Spring Lane to Glenwood Avenue.

  • Monday-Friday: Northbound lane closures (right lane only) for electrical work on York Road from 43rd Street to E. Cold Spring Lane.
The MTA bus stops will not be affected. The construction work will be completed in sections to reduce the impact on traffic.

For additional information or questions regarding this work, please contact Mrs. Jessica Lewis
at 410 396-6956.  