Tuesday, May 22

York Road Streetscape Update: Week of May 21


WORK PLANNED FOR UPCOMING WEEK (weather permitting)

May 21 – May 25, 2012


Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
           

  • Monday-Friday: Southbound lane closure for concrete work (sidewalk, curb, driveways) on York Road between Glenwood Avenue and E. Cold Spring Lane. Once this is completed, there will be a northbound lane closure for concrete work (sidewalk, curb, driveways) on York Road between 43rd Street and E. Cold Spring Lane.

  • Monday-Friday: Southbound lane closure (parking lane only) for electrical work on York Road between E. Cold Spring Lane and 43rd Street


*****There will be limited parking between 43rd Street and E. Cold Spring Lane due to construction activities. There may be parking where the contractor is not actively working*****


The MTA bus stops will not be affected. The construction work will be completed in sections to reduce the impact on traffic.

Thank you in advance for your cooperation. For additional information or questions regarding this
work, please contact Mrs. Jessica Lewis at 410 396-6956.  