Friday, July 20

York Road Streetscape Update: Week of July 23


WORK PLANNED FOR UPCOMING WEEK (weather permitting)

July 23 – July 27, 2012


Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
           

  • Monday-Friday: One lane closure for concrete work (sidewalk, curb, and driveways) on York Road between E. Cold Spring Lane and Glenwood Avenue.

  • Monday-Friday: One lane closure for electrical work on York Road between 43rd Street and E. Cold Spring Lane


The MTA bus stops will not be affected. The construction work will be completed in sections to reduce the impact on traffic.

Thank you in advance for your cooperation. For additional information or questions regarding this
work, please contact Mrs. Jessica Lewis at 410 396-6956. 