Monday, November 5
York Road Streetscape Update: Week of November 5
WORK PLANNED FOR UPCOMING
WEEK (weather permitting)
November 5 – November 9,
2012
Contract TR-10319- York Road
Rehabilitation
Limits: York Rd from 43rd Street to Glenwood Avenue
Work Hours: 8:00 am to
3:00 pm (northbound only - As per Robert Ferguson)
9:00 am to 4:00 pm
(southbound only - As per Robert Ferguson)
Monday-Friday: One lane
closure for concrete work (sidewalk, curb, and driveways) structure
adjustments, and base repairs between E.
Cold Spring Lane and Glenwood Avenue .
Monday-Friday: Tree
planting/landscaping between 43rd
Street and Glenwood Avenue .
Landscaping goal…ten trees
per day!
Electricians will be on
site. If banners are removed…they WILL
be REPLACED.
The MTA bus stops will not
be affected. The construction work will be completed in sections to reduce the
impact on traffic.
Thank you in advance for
your cooperation. For additional information or questions regarding this work,
please contact Mrs. Jessica Lewis at 410 396-6956.