WORK PLANNED FOR UPCOMING WEEK (weather permitting)

November 12 – November 16, 2012


Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
           

  • Monday-Friday: One southbound lane closure for concrete work (sidewalk, curb, and driveways) between E. Cold Spring Lane and Glenwood Avenue.

  • Monday-Friday: One lane closure for base repairs (electrical crossings) between E. Cold Spring Lane and 43rd Street.

  • Monday-Friday: One lane closure for milling between Homeland Ave and Winston Ave.

  • Monday-Friday: One parking lane (moveable) closure for tree planting/landscaping between 43rd Street and Glenwood Avenue.

  • Monday-Friday: The electricians will be onsite installing pedestrian poles. No lane closure required.
The MTA bus stops will not be affected. The construction work will be completed in sections to reduce the impact on traffic.

Thank you in advance for your cooperation. For additional information or questions regarding this
work, please contact Mrs. Jessica Lewis at 410 396-6956.  

The Department of Transportation: “Keeping Baltimore Moving Safely”