WORK PLANNED weather permitting)
October-November, 2013
Contract TR-10319- York Road
Rehabilitation
Limits: York Rd from 43rd Street to Glenwood Avenue
Work Hours: 8:00 am to 3:00 pm
(northbound only - As per Robert Ferguson)
9:00 am to 4:00 pm (southbound only -
As per Robert Ferguson)
Tentative Schedule:
10/19/13: Signal Activation
10/21-10/23/13: Remove Old Signal Equipment
10/24-11/8/13: Remove existing concrete & install new
ADA compliant ramps, curb & sidewalk
11/11-11/13/13: Mill Cold Spring, Old Cold Spring (patch)
& crosswalks at 43rd St
11/14-11/15: Adjust
manholes in the intersection of Cold Spring & York
11/18-11/21/13: Pave milled areas
Thank you in
advance for your cooperation. For additional information or questions regarding
this
work, please
contact Mrs. Jessica Lewis at 410 396-6956/6957.
The
Department of Transportation: “Keeping Baltimore Moving Safely”
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment