WORK PLANNED weather permitting)

October-November, 2013


Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
           
Tentative Schedule:

10/19/13: Signal Activation

10/21-10/23/13: Remove Old Signal Equipment

10/24-11/8/13: Remove existing concrete & install new ADA compliant ramps, curb & sidewalk

11/11-11/13/13: Mill Cold Spring, Old Cold Spring (patch) & crosswalks at 43rd St

11/14-11/15:  Adjust manholes in the intersection of Cold Spring & York

11/18-11/21/13: Pave milled areas


Thank you in advance for your cooperation. For additional information or questions regarding this
work, please contact Mrs. Jessica Lewis at 410 396-6956/6957.  