Monday, September 17

York Road Streetscape Update: Week of September 17



WORK PLANNED FOR UPCOMING WEEK (weather permitting)

September 17 – September 21, 2012


Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
           

  • Monday-Friday: One southbound lane closure for concrete work (sidewalk, curb, and driveways) on York Road between E. Cold Spring Lane and Glenwood Avenue.

  • Monday-Friday: One northbound lane closure for concrete work (bus pads only) on York Road at Winston Ave and at Cold Spring.

  • Monday-Friday: Electrical contractor will be onsite installing pedestrian poles (push button poles) and joint use poles (signal/lighting poles) at numerous places along York Road.
  
The MTA bus stops will not be affected. The construction work will be completed in sections to reduce the impact on traffic.

Thank you in advance for your cooperation. For additional information or questions regarding this
work, please contact Mrs. Jessica Lewis at 410 396-6956.  