WORK PLANNED FOR UPCOMING WEEK
(weather permitting)
October 15 – October 18, 2012
Contract TR-10319- York Road
Rehabilitation
Limits: York Rd from 43rd Street to Glenwood Avenue
Work Hours: 8:00 am to 3:00 pm
(northbound only - As per Robert Ferguson)
9:00 am to 4:00 pm (southbound only -
As per Robert Ferguson)
- Monday-Friday: One lane closure for concrete work
(sidewalk, curb, and driveways) and structure adjustments between E. Cold
Spring Lane and Glenwood Avenue.
- Monday-Friday: One lane closure for tree
planting/landscaping between 43rd Street and Glenwood Avenue.
- Monday-Friday: The Electricians will be onsite
pulling wire from light poles to handboxes at various locations.
The MTA bus stops will not be
affected. The construction work will be completed in sections to reduce the
impact on traffic.
Thank you in
advance for your cooperation. For additional information or questions regarding
this
work, please
contact Mrs. Jessica Lewis at 410 396-6956.