Monday, October 15

York Road Streetscape Update: Week of October 15




WORK PLANNED FOR UPCOMING WEEK (weather permitting)

October 15 – October 18, 2012


Contract TR-10319- York Road Rehabilitation

Limits: York Rd from 43rd Street to Glenwood Avenue

Work Hours: 8:00 am to 3:00 pm (northbound only - As per Robert Ferguson)
                      9:00 am to 4:00 pm (southbound only - As per Robert Ferguson)
           

  • Monday-Friday: One lane closure for concrete work (sidewalk, curb, and driveways) and structure adjustments between E. Cold Spring Lane and Glenwood Avenue. 
  • Monday-Friday: One lane closure for tree planting/landscaping between 43rd Street and Glenwood Avenue.
  • Monday-Friday: The Electricians will be onsite pulling wire from light poles to handboxes at various locations.
The MTA bus stops will not be affected. The construction work will be completed in sections to reduce the impact on traffic.

Thank you in advance for your cooperation. For additional information or questions regarding this
work, please contact Mrs. Jessica Lewis at 410 396-6956.  


The Department of Transportation: “Keeping Baltimore Moving Safely”